11/01/17

On-site progress

Works to the Woodside Grove apartment blocks are now in the final stages in terms of decorations and floor finishes. Scaffolds have been taken down and external landscape works have now commenced in preparation for handover. While in the Houses, all the roof work is complete as well as external brickwork. Windows are currently being installed and internal fit out is ongoing.

The Garden Apartments external brickwork is taking shape and the internal fit out also moving onwards.

Structural framework to the Gatehouse is now complete and brickwork has commenced with external scaffolding to follow. While in The Avenue houses, final sections of pre cast flooring units should be complete by the middle of January with structural roof works and finishes to follow.

The roofs of The Heritage Buildings have been stripped back; new structural steelwork has been installed with timberwork and finishes to follow. Once the roofs have been installed the internal fit out can commence with new floor joists and basement works progressing at the same time.

Our sales and marketing suite is open, if you’d like to visit please contact the sales team on 0208 501 8777 or enquiries@woodsidesquare.co.uk.